MAY-2004

REPSOL YPF - Santa Cruz, Bolivia

Project: “Process Gas and Fluid Measuring, Margarita Plant - Repsol YPF”

Detail engineering, provision, installation and testing, and start-up of 6 gas and fluid ultrasonic meters for the process control and matter balance at the Margarita Plant.

MAY-2004

COBEX - Santa Cruz, Bolivia

Elaboration of the Engineering project for the installation of a Natural Gas System for the Automobile Battery Plaques Manufacture Plant. The system includes an external Pipeline of 2,300 mts. and a conditioning, regulation and measuring system.

MAY-2004

CLHB - Santa Cruz, Bolivia

Installation of Seven Temperatura Mechanic Compressors ATGs, brand FMC Smith Meter, for the product dispatch to temperature corrected volumes @ 60º F, at the Remote Loading Terminals of Monteagudos, Camiri and Villamontes.
MAR-2004

GRAVETAL- Puerto Suárez - Santa Cruz, Bolivia

Engineering, design and construction of a natural gas measuring system for process measuring and process control of ovens.

DEC-2003

SAINCO - TOTAL SERVICES,TRANSREDES S.A. – Santa Cruz, Bolivia

Pre-commission and commissioned of the instrumentation and installation of actuators for ESD valves for the “ESD Safety System Phase III, for the Sica-Sica. Torre Pampa, Oruro and Safari I Stations” for TRANSREDES.

DEC-2003

CLHB - Santa Cruz, Bolivia

Customization of the Palmasola loading Terminal, installation of an electronic pre-selector Accuload II Version STM
DEC-2003

CLHB - Santa Cruz, Bolivia

Technical Report of the Monteagudo, Camiri, Villamontes, Puerto Villarroel, San Jose, and Riberalta loading terminals.